+ | ==Fri Oct 2== | ||
+ | * 11:30a - 1:15p | ||
+ | ** review AVR report from PCB fab house. Errors need to be correct and resubmitted. | ||
+ | |||
==Thur Oct 1== | ==Thur Oct 1== | ||
* 9-10:30 | * 9-10:30 |
Revision as of 17:14, 2 October 2009
Contents
Oct 09
Fri Oct 2
- 11:30a - 1:15p
- review AVR report from PCB fab house. Errors need to be correct and resubmitted.
Thur Oct 1
- 9-10:30
- improve gnd grid, add plane for switcher, and correct poor routing issues w/WIP4C1.
- 4-8:15
- improve manual routing of WIP4C1, manual route of VCC33, re run auto route
- create a dclamp2 -
- submit project to fab house for DRC analysis
- 9:30p - 2:15 a
- review time drif experiment and improve output and start plotting
- test LF, checking output data, build new envelope for 2000N
- setup testjig to monitor copley (required reboot and serial cable was moved)